Summary. Development is a sequence of options in which the developer buys time to answer questions before committing capital, and the failures are almost always a question answered too late — title exceptions discovered after closing, an environmental condition found after the innocent landowner defense was lost, an entitlement the site could not obtain, a construction loan that funded before the equity was documented. This toolkit follows a project from site identification through disposition: structuring the acquisition, running title, survey, and environmental review, obtaining entitlements, assembling the capital stack and the joint venture, financing and building, stabilizing, and exiting.
What this toolkit is for, and who should use it
A development deal is a series of go/no-go decisions in which each stage costs more than the last. The discipline is to answer the killing questions in the cheapest stage — is the site entitleable, is the title insurable, is there contamination, will the numbers work at achievable rents — before the deposit goes hard and long before the construction loan closes.
This toolkit is for developers, owner-users building for their own occupancy, investors, and the counsel advising them, on a commercial or multifamily project of modest to middle scale.
Roadmap at a glance
- Feasibility and site selection.
- The acquisition agreement — the diligence period as a purchased option.
- Title and survey.
- Environmental review.
- Zoning and entitlements.
- Design and construction contracting.
- The capital stack — debt and equity.
- The joint venture agreement.
- Construction financing and closing.
- Building — draws, changes, and lien management.
- Stabilization — certificate of occupancy, permanent financing, and leasing.
- Disposition, and the questions developers ask.
Stage 1 — Feasibility
Before anything is signed, answer: what can be built here, what will it cost, and what will it be worth?
Market — absorption, achievable rents or sale prices, competitive supply, and demand drivers. Physical — topography, soils, access, utilities capacity, floodplain, wetlands, and any endangered species or historic constraints. Regulatory — the current zoning, what the comprehensive plan contemplates, and what a rezoning or a variance would realistically require. Financial — a pro forma with development cost, an interest reserve, lease-up assumptions, an exit capitalization rate, and a sensitivity analysis at plus and minus 15 percent on cost and rents. Timing — entitlement duration, construction duration, and lease-up, because carry cost during entitlement is where marginal deals die.
Form the entity — typically a single-purpose LLC per project, which isolates liability, facilitates financing, and simplifies a later sale.
Stage 2 — The acquisition agreement
The diligence period is the point of the agreement. The developer is buying an option: an earnest money deposit at risk in exchange for a defined period to answer the killing questions, with a right to terminate and recover the deposit.
Negotiate: the length of the diligence period, realistically scoped to the actual work; extensions for additional deposits; when the deposit goes hard; access rights for inspections, borings, and environmental sampling, with the indemnity and insurance the seller will require; the closing date and any extension rights; and the seller's representations — title, environmental, litigation, leases, service contracts, and code violations — with a survival period.
Consider an entitlement contingency where the deal depends on obtaining approvals, with the developer controlling the application and the seller obligated to cooperate. Consider a feasibility contingency giving the developer sole discretion during the period, which is standard and which sellers resist.
Address the 1031 exchange possibility, cooperation obligations, and any assignment right to a project entity or a joint venture.
Stage 3 — Title and survey
Order the title commitment immediately, and read Schedule B — the exceptions — line by line rather than accepting a summary.
Obtain and read the underlying documents for every exception: easements, covenants and restrictions, reciprocal easement agreements, mineral reservations, and any prior deeds with reversionary or restrictive language. An exception nobody read is the most common expensive surprise in a land acquisition.
Order an ALTA/NSPS survey and confirm it locates the exceptions on the ground. A recorded easement that runs through the building envelope is a design problem or a deal problem, and it is visible only when the survey and the title work are read together.
Negotiate title endorsements: zoning (including a 3.1 or 3.2 with parking and setback coverage), access, contiguity, survey, comprehensive, subdivision, and — for the lender — the endorsements its counsel requires.
Address utility availability and capacity through will-serve letters, and access to a public right of way, both of which are frequently assumed and occasionally absent.
Stage 4 — Environmental review
Order a Phase I Environmental Site Assessment meeting the ASTM standard, which supports the all appropriate inquiries requirement for the innocent landowner, bona fide prospective purchaser, and contiguous property owner defenses under CERCLA. The inquiry must be completed before acquisition; the defense is not available retroactively.
Where the Phase I identifies a recognized environmental condition, order a Phase II with sampling. Then decide: terminate, negotiate a price reduction, require remediation before closing, obtain a no further action letter or entry into a voluntary cleanup program, or allocate the risk through an indemnity backed by security and — where the exposure is material — environmental insurance.
Confirm wetlands delineation and any Section 404 permitting, floodplain status and any required elevation, endangered species and cultural resource constraints, and any asbestos, lead, or radon issues in an existing structure.
Preserve the continuing obligations the CERCLA defenses require — reasonable steps, cooperation, and compliance with land use controls — because the defense is lost by failing them after closing.
Stage 5 — Zoning and entitlements
Confirm the current zoning and whether the intended use is permitted by right, conditionally, or not at all.
Where relief is needed, identify the vehicle: a rezoning, a variance (which requires a hardship showing that is difficult in most jurisdictions), a conditional use permit, a special exception, a planned unit development, or a comprehensive plan amendment.
Map the process: staff review, planning commission, governing body, and any design review, historic, or architectural board — with the statutory notice, hearing, and appeal periods, and the realistic timeline including continuances.
Address subdivision or platting, site plan approval, and any development agreement — which can fix the applicable regulations, phase obligations, and allocate infrastructure responsibility, and which is worth pursuing where the project is large enough to justify it.
Understand the exactions and impact fees, and the constitutional limits: an exaction must bear an essential nexus to a legitimate state interest (Nollan v. California Coastal Commission, 483 U.S. 825 (1987)) and be roughly proportional to the impact (Dolan v. City of Tigard, 512 U.S. 374 (1994)), with those requirements applying to legislatively imposed conditions as well.
Address community engagement deliberately. Entitlements are political as well as legal, and organized opposition defeats more projects than legal deficiencies do.
Confirm vesting — when the developer's rights become protected against a later change in the rules — which is a matter of state law and of the development agreement.
Stage 6 — Design and construction contracting
Engage the design professional with a negotiated agreement covering scope (including construction administration, which owners cut and then need), the standard of care rather than a warranty, a limitation of liability tied to insurance limits, insurance with an adequate retroactive date, a document license permitting completion by another designer, and dispute resolution aligned with the construction contract.
Select the delivery method — design-bid-build, design-build, or CM at risk — and structure the price, with the contingency held by the owner and the basis of any GMP defined by a specific document set plus a written assumptions list.
Negotiate the contract provisions that decide claims: order of precedence, a CPM schedule with monthly updates that will actually be enforced, changes with capped markups, differing site conditions, delay and concurrency, liquidated damages supported by a documented calculation, notice provisions, retainage, and lien waiver requirements from every tier.
Resources
- Managing a Construction Project from the Owner's Side
- Construction Project Toolkit: A Roadmap for Owners
Stage 7 — The capital stack
Senior construction debt, typically 55 to 70 percent of cost, with the terms described in the lending materials — interest reserve, draw mechanics, a completion guaranty, a carry guaranty, and bad boy carve-outs converting a nonrecourse loan to recourse on defined events including an unauthorized transfer, an additional lien, a voluntary bankruptcy filing, or misapplication of insurance or condemnation proceeds.
Mezzanine debt or preferred equity filling the gap, with an intercreditor agreement governing standstill, cure rights, and the mezzanine lender's right to foreclose on the equity.
Common equity — the sponsor's co-investment and the limited partners' capital.
Other sources by project type: tax increment financing, low-income housing tax credits, historic rehabilitation credits, New Markets Tax Credits, opportunity zone equity, PACE financing, and grant programs — each of which brings its own compliance regime and its own restrictions on transfer.
Confirm the securities analysis for any equity raise: a Regulation D private placement with accredited investor verification for Rule 506(c), a Form D filing, state blue sky notices, and a private placement memorandum with real risk disclosure.
Stage 8 — The joint venture agreement
Capital — initial contributions, the obligation and mechanics for additional capital calls, and the consequences of failing to fund: dilution, a punitive dilution formula, or a member loan at a high rate. This provision decides who ends up owning the project when a cost overrun arrives.
The distribution waterfall — return of capital, a preferred return and whether it compounds, an IRR hurdle structure, the promote or carried interest to the sponsor, and any clawback. Model it at several outcomes, because waterfalls that look identical in a term sheet diverge substantially at a 12 percent IRR versus a 22 percent one.
Control — major decisions requiring investor consent, the sponsor's day-to-day authority, and a deadlock mechanism.
Sponsor obligations — the guaranties, the development fee, the property management or asset management fee, and any affiliate contracts, which should be at market and disclosed.
Removal of the sponsor for cause, defined precisely.
Transfer restrictions, rights of first refusal, buy-sell provisions, drag-along and tag-along rights, and the exit mechanism.
Stage 9 — Construction financing and closing
The loan closing is the point where everything assembled above is tested. Expect the lender to require: the entity documents and authority; the title policy with the lender's endorsements; the survey; the environmental report and, frequently, a reliance letter; the appraisal; the construction contract and the plans; the architect's agreement with a consent to assignment; the budget and draw schedule; the schedule; permits; insurance including builder's risk with the lender as loss payee; a flood determination; the guaranties; subordination and non-disturbance agreements for any leases; and an opinion of counsel.
Start the long-lead items early — the title endorsements, the environmental reliance letter, and the architect's consent take weeks and are the usual cause of a delayed closing.
Stage 10 — Building
Draw administration — the lender's inspector, the title company's date-down endorsements, and the lien waivers from every tier each period. Confirm the unconditional prior-period waiver, which proves the money reached the lower tiers.
Change orders priced against the contract methodology, with the contingency drawn only under the defined criteria and with the lender's consent where the loan requires it.
Schedule and delay — enforce the schedule update requirement from month one, because it is the evidence in every delay dispute.
Lien management — understand the state's mechanic's lien priority rules relative to the mortgage, and whether a lien relates back to the commencement of work, which in some states can prime a construction mortgage recorded afterward.
Insurance maintained and endorsements confirmed at each renewal.
Stage 11 — Stabilization
Certificate of occupancy and all permit closeouts, plus any conditions of approval that must be satisfied before or at occupancy — landscaping, off-site improvements, and dedications.
Punch list and closeout — as-builts, O&M manuals, assigned warranties, commissioning, and final unconditional lien waivers before final payment, with any owner claims reserved in writing.
Permanent financing or a loan conversion, with the rate lock, the debt service coverage and loan-to-value tests, and the timing relative to the construction loan maturity.
Leasing — the form lease, the leasing guidelines the lender approved, tenant improvement allowances and their funding, SNDAs and estoppels, and the rent roll that will support the permanent loan and the eventual sale.
Operations — property management, insurance, property tax appeal if the assessment overshoots, and the eleven-month warranty walkthrough before the correction period expires.
Stage 12 — Disposition, and the questions developers ask
Exit options: a sale, a refinance and hold, a recapitalization, or a contribution to a larger vehicle. Prepare as for any sale — clean books, a complete rent roll with estoppels, assignable contracts, and a due diligence package assembled in advance.
Tax — the 1031 exchange timeline (45 days to identify, 180 days to close) and its requirements; depreciation recapture; the treatment of the carried interest and the three-year holding period under 26 U.S.C. § 1061; and, where applicable, opportunity zone holding requirements.
"How long does entitlement take?" Six months for an administrative approval in a supportive jurisdiction; two to four years for a contested rezoning. Carry cost during that period is where marginal deals die, which is why the entitlement risk should sit in an option or a contingency rather than in owned land.
"Should the deposit go hard?" Only after the killing questions are answered — title, environmental, and entitlement feasibility. Sellers push for it early; extensions for additional deposits are the usual compromise.
"Who signs the guaranties?" The sponsor, personally or through a creditworthy entity, for completion, carry, and the bad boy carve-outs. Negotiate burn-offs on completion and on stabilization, and negotiate several rather than joint liability among multiple sponsors.
"What is the most common expensive surprise?" A title exception nobody read, or an environmental condition discovered after the Phase I window closed. Both are avoidable in the diligence period, which is what the deposit purchased.
Master resource index
Articles
- Commercial Leases for Small Businesses: What to Negotiate Before You Sign
- Premises Liability for Property Owners and Businesses
- Bank Loan Workouts, Forbearance, and Receiverships
Guides
- Managing a Construction Project from the Owner's Side
- Negotiating a Commercial Loan Term Sheet
- Buying a Home: Contract, Inspection, Title, Financing, and Closing
Checklists
- Commercial Loan Closing Checklist
- Commercial Lease Review Checklist
- Regulation D Private Placement Checklist
- Insurance Program Review Checklist
Related toolkits
- Construction Project Toolkit: A Roadmap for Owners
- Commercial Leasing Toolkit
- Business Formation and Entity Maintenance Toolkit
- Debt Restructuring and Workout Toolkit
External and primary sources
- CERCLA, 42 U.S.C. § 9601 et seq., including the innocent landowner, bona fide prospective purchaser, and contiguous property owner defenses and the all appropriate inquiries rule, 40 C.F.R. Part 312; ASTM E1527 Phase I standard
- Clean Water Act § 404, 33 U.S.C. § 1344; Endangered Species Act, 16 U.S.C. § 1531 et seq.; National Historic Preservation Act § 106
- Nollan v. California Coastal Commission, 483 U.S. 825 (1987); Dolan v. City of Tigard, 512 U.S. 374 (1994); Penn Central Transportation Co. v. New York City, 438 U.S. 104 (1978)
- Securities Act of 1933 and Regulation D, 17 C.F.R. §§ 230.500–230.508; 26 U.S.C. §§ 1031, 1061, and 1400Z-2
- State zoning enabling acts, subdivision statutes, vesting statutes, and mechanic's lien priority rules
This toolkit is educational and not legal advice. Land use, environmental, lien priority, and vesting rules vary substantially by state and locality, and tax treatment depends on the specific structure. Consult qualified real estate, environmental, and tax counsel before acquiring a site or closing a construction loan.